
Lit May 2, 1944
Extinguished June 25, 1967
Relighting September 24, 2005 |
Avery
Point Lighthouse
- APLS
|
Construction Updates
In May of this year, the contract for the first primary phase of restoration of the lighthouse awarded to Kronenberger & Sons Restoration, Inc.
of Middletown, Connecticut.
Kronenberger & Sons Restoration, Inc., founded in 1946, is a
three-generation firm specializing in the restoration, preservation and
adaptive re-use of period structures. Many of their clients have included
museums, municipalities, architects, historical societies and homeowners.
Their work has included projects involving National Historic Landmark
Buildings, National Historic American Buildings, and buildings listed on the
National Register of Historic Place in Connecticut, Massachusetts and New
York. Some of the projects they have completed include barns, carriage houses,
covered bridges, churches, town halls and a vast array of period homes and out
buildings.
In early June, while conducting a cursory inspection of the lighthouse, it
was discovered that one of the marble balusters on the balustrade on top of
the lighthouse was in danger of falling. (See Photo) This
condition was immediately reported to the University of Connecticut with a
request that the balusters be secured to prevent the loss of these very
historically significant pieces of artwork. (NOTE: These balusters, which were
imported from Italy, were once used to decorate the beautiful gardens of the
original occupant of the Avery Point property.
Upon being advised of the baluster problem, a “change order” to the initial
restoration work contract was initiated and all scheduled work on the
lighthouse was placed on hold until this issue was resolved. After receiving
recommendations from engineers, the University accepted and authorized a
change order which consisted of constructing a wooden barrier in front and in
back of the balusters using threaded rods to secure and stabilize the
balusters. (See photo) Cost of erecting the barrier, including materials was $4,790.00.
On June 26, 2003 the lantern room was moved from the University of
Connecticut’s Avery Point campus in Groton. To facilitate moving the structure
along highways and to avoid the interference with electric power lines, it was
necessary to remove the roof from the main structure of the lantern room. The
roof and main structure of the lantern room were then loaded onto two trailers
and, under police escort, was brought to the West Mystic Wooden Boat Building
Company in West Mystic, Connecticut.
(Photo A) (Photo B)
The old structure will be used as a template to produce a new [duplicate]
lantern room.
The West Mystic Boat Building Company, through its owner Professor Steve
Jones, has graciously offered to build a duplicate of the lantern room for the
cost of materials only. It is estimated that the savings resulting from the
“in-kind” donation to provide the labor to build the new lantern room will be
approximately $15,000 to $20,000.
Within one week after the arrival of the lantern room at the boat company
work was initiated. It is anticipated that the new lantern room will be
completed by mid-October. Photographs of the progress on the lantern room are
attached. (Photo A)
(Photo B) (Photo C)
Special replacement blocks for the main structure of the lighthouse have
been manufactured by the Durastone, Inc. of South Portland, Maine. Because the
lighthouse was constructed using six different size and shaped blocks special
molds had to be constructed. A total of three hundred molds of the six
different sizes and shapes were made to expedite and mass produce the 3,000
blocks needed for the restoration of the lighthouse.
On August 22, 2003, members of APLS were present at the Durastone, Inc. and
witnessed the pouring of the first replacement blocks.
(See photo) The first delivery of blocks was received at the lighthouse on September 9th
and were accepted and approved by the project engineers for installation.
NOTE: Prior to beginning the installation of the blocks, a four foot square
test section of blocks, using a special cement mortar, was constructed to
permit engineers to inspect and approve the mortar.
(See photo)
Installation of the blocks could not begin until the mortar was approved on
September 15th.
The process of replacing the existing block began on September 15th and
completion is anticipated by Thanksgiving of this year.
The block restoration process requires the removal of approximately one
half of the depth of the face of each block.
(See photo) The new [solid] half-blocks are then installed in front of the old blocks and
the void of the older block filled with cement.
(See photo)
|
~~~ Home ~~~
|